UKH Journal of Science and Engineering | Volume 5 • Number 1 • 2021 93
2.1.2. Training Form
Staff members who lacked experience and were not qualified to join the work in the strategic project, were directed to
take training programs that were prepared by the the one responsible for the activity under supervision of the QA Unit.
In total, 53 forms were filled; however, among them 6 of the staff failed the training and were not allowed to join the
project, see Table 1.
2.1.3. Calibration Form
All equipment used in the project was subjected to calibration when needed. The details of calibration were checked by
using the equipment manual; those that needed continuous calibration, the duration was added in the form. In total, 15
forms were filled in. Special calibration stickers were used for each equipment to indicate the date and duration of the
calibration.
2.1.4. Work Progress Forms
Three types of Work Progress forms were used by QA Unit personnel, see Table 1. The follow-up of the performed
work at each of the six activities in the field, laboratories and office work by the QA Unit personnel was done using the
three forms. In total, 1558, 349 and 378 forms were filled in for field, office and laboratory work, see Table 1. Figure 1
is an example of the Field Work Visit Form, those of Office and Laboratory forms are slightly different.
2.1.5. Work Completion Form
This form was filled in by the QA Manger (the current author) for each completed work item mentioned in the strategic
project depending on the bill of quantities mentioned in the contract. Each form was signed by the Activity Responsible,
QA Manger and the Project Manager, and a copy was submitted to the Client. In total 96 forms were filled in, see Table
1.
2.1.6. Verification Form
This form was filled in by the QA Manager during checking the verification of any work (field, office and laboratory).
The type of verification and the verifier person; usually the QC of the activity are mentioned in the form, besides
mentioning the title and serial number of the work procedure. In total, 67 forms were filled in, see Table 1.
2.1.7. Committee Meeting Form
A special Reviewing Committee was established in the strategic project. The Activity Responsible, QA Manager and the
Project Manager with the deputy were the committee members. However, occasionally, some specialists were invited
from Headquarters of GEOSURV to join the committee. The date, time, duration, purpose, and members in attendance
of the meeting were mentioned in the form Figure 2. The form was filled in by the QA Manager according to the request
of the Project Manager or the deputy and/or any the one responsible for the activity. Occasionally, meetings were
conducted upon the request of the Client’s responsible. In total 31 forms were filled in, see Table 1.
2.1.8. Reviewing Committee Form
All conducted reports were reviewed by the committee; accordingly, the authors of the reviewed report should amend
the report by considering the forwarded comments by the committee members. However, when the authors were not
in accordance with a comment or more, then the committee members have to decide which opinion is the right. A total
of 20 forms were filled in, see Table 1.
2.1. 9. Nonconformance Form
A nonconformance case is when any field, office or laboratory work is performed with deviation from the involved
work procedure, also called “Defect” (Hoyle, 2009; Mitra, 2016). One of the main aims of following-up the work
progress in the field, office and laboratory by the QA Unit’s personnel using the work progress forms and depending
on the work procedures, is to discover any Nonconformance, accordingly a Nonconformance Form was used Figure 3.
The recognition of a nonconformance case by the QA Unit’s personnel before being recognized by the Client’s
responsible was one of the main aims of implementing the QA Program in the strategic project. The type of
nonconformance, date, work responsible and the one responsible for the activity are mentioned in the form Figure 3.
Also, the required corrective actions, which are necessary to overcome the nonconformance case and performing the
work according to the involved work procedure. Moreover, it is also shown if the Nonconformance was recognized by
the Client’s responsible or otherwise. In total, 3 forms were filled in, see Table 1.
2.2. Work Procedure
A work procedure was prepared for each performed item in the strategic project. The one responsible for the activity
with the collaboration of the activity experienced staff, prepared work procedures which had to be followed by the
activity staff members. Moreover, the QA Unit’s personnel used the work procedures to follow-up the work progress.
Each procedure included: 1) The required specialization and scientific degree of staff who can perform the concerned
work, 2) Step by step description how to perform the concerned work, 3) If equipment needed to perform the concerned
work, then the details of the equipment are mentioned, and if calibration is needed, then the calibration procedure and
duration are mentioned, 4) If certain work needs certain time interval for performance, then the time interval is